2015 CH Overlay Projects

  • Construction Year: 2015
  • Community: Throughout Scott County
  • Corridors Served: CH 2, CH 14, CH 16, CH 17, CH 42, CH 64
  • Project Lead: Scott County
Overlay Projects
CH 2: Between CH 11 & CH 15 in Helena Township
  • Start Date: July 15
  • Completed: September 2015
CH 14: Between CH 15 & CH 17 in Louisville Township
  • Start Date: July 23rd
  • Completed: September 2015
CH 16: Located East of CH 17 in Shakopee
This will be a Left turn lane to St. Francis Emergency Room:
  • Start Date: June 23, 2015
  • Completed: August 2015
CH 17: between 10th Avenue & CH 101 in Shakopee
  • Start Date: June 29, 2015
  • Completed: August 2015
CH 42: Located at Louisiana Avenue in Savage
  • Start Date: June 23, 2015
  • Completed: August 2015
CH 64: Between CH 11 & TH 21 in Helena Township
  • Start Date: Mid August 2015
  • Completed: Mid-October 2015

Purpose & Justification
This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular-basis to preserve the initial paving investment and provide additional safety enhancements. For more information please view the 2015 Overlay Map (PDF).