2018 Overlays on CH 2, CH 16, CH 21, CH 81

  • ​Construction Year: 2018
  • Community: Throughout Scott County
  • Corridors Served:
  • Project Lead: Scott County
  • Contractor: Valley Paving, Inc.
Overlay Projects 

CH 2: From CH 23 to CH 27


  • Start Date: May 14, 2018
  • Traffic Control Changes: Road is open to through traffic. 
  • Work Description: Work is complete. 
  • Completion Date: September 21, 2018

CH 16: From CH 15 to CH 17


  • Start Date: August 13, 2018
  • Traffic Control Changes: There may be delays up to 5 minutes on the side streets as the paver and rollers pass through the intersections.
  • Work Description: Wet weather has delayed the final lift of asphalt between Marystown Road and CH17 (Marschall Road). Paving is currently scheduled for Monday, Sept 24 and Tuesday, Sept 25. 
  • To Be Completed by: September 30, 2018

CH 21: From Lakeside Avenue to CH 42


  • Start Date: June 2018
  • Traffic Control Changes:  Expect intermittent lane closures. 
  • Work Description: Work is complete. 
  • To Be Completed by: September 1, 2018

CH 21: From Adelmann to CH 27


  • Start Date: June 2018
  • Completed

CH 81: From CH 8 to TH 13

  • Start Date: May 21, 2018
  • Work Description:  Paving is complete
  • Completion Date: September 2018
  • Traffic Control Changes: 
    • CH 81 From CH 10 to TH 13 is open to traffic. 
    • CH 81 From CH 8 to CH 10 is open to traffic. 

    ​Purpose & Justification

    This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.

  1. Len Laxen

    Construction Manager

  2. Highway Department


    Physical Address
    600 Country Trail East
    Jordan, MN 55352


    Directions

    Phone: 952-496-8346