2018 Overlays on CH 2, CH 16, CH 21, CH 81

  • ​Construction Year: 2018
  • Community: Throughout Scott County
  • Corridors Served:
  • Project Lead: Scott County
  • Contractor: Valley Paving, Inc.
Overlay Projects 

CH 2: From CH 23 to CH 27

  • Start Date: May 14, 2018
  • Traffic Control Changes: Road is open to through traffic. 
  • Work Description: Work is complete. 
  • Completion Date: September 21, 2018

CH 16: From CH 15 to CH 17


  • Start Date: August 13, 2018
  • Traffic Control Changes: There may be delays up to 5 minutes on the side streets as the paver and rollers pass through the intersections.
  • Work Description: Wet weather has delayed the final lift of asphalt between Marystown Road and CH17 (Marschall Road). Paving is currently scheduled for Monday, Sept 24 and Tuesday, Sept 25. 
  • Completion Date: September 30, 2018

CH 21: From Lakeside Avenue to CH 42


  • Start Date: June 2018
  • Traffic Control Changes:  Expect intermittent lane closures. 
  • Work Description: Work is complete. 
  • To Be Completed by: September 1, 2018

CH 21: From Adelmann to CH 27


  • Start Date: June 2018
  • Completed Work is complete.

CH 81: From CH 8 to TH 13

  • Start Date: May 21, 2018
  • Work Description:  Paving is complete
  • Completion Date: September 2018
  • Traffic Control Changes: 
    • CH 81 From CH 10 to TH 13 is open to traffic. 
    • CH 81 From CH 8 to CH 10 is open to traffic. 

    ​Purpose & Justification

    This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.