CH 2 & CH 91 Roundabout

  • Construction Year: 2020
  • Community: City of Elko New Market
  • Corridor Served: CH 2 & CH 91
  • Project Design Lead: City of Elko New Market
  • Project Construction Lead: Scott County
  • Contractor: Ryan Contracting Company
  • Start Date: May 2020

Current Traffic Impacts:


Mon, June 15, 2020: Full road closure at intersection of CH 2 and CH 91 for approximately 10 weeks, weather permitting, to construct roundabout. Detour map shows both north/south and east/west options. See detour map [PDF].

Project Updates:


June 30, 2020: Storm sewer work has begun and will continue for the next two weeks, followed by construction of the roundabout and road work.
July 10, 2020: Crew wrapping up storm sewer installation and will be moving on to grading work.

Description


Improving the safety and operations of the intersection at County Highway 2 and 91 in the City of Elko New Market. This project will reconstruct the intersection as a partial multi-lane roundabout and is programmed for construction in 2020.
  

Purpose & Justification


Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.

Project Schedule

  • Preliminary Design: Summer 2019
  • Final Design: Winter 2019
  • Right-of-Way/Easement Acquisition: Fall/Winter 2019
  • Construction: Spring 2020

Detour Map: Starts June 15, 2020

CH 2 CH 91 Closure Detour Map

Construction Drone Footage

Drone Progress Photos June 24, 2020

Project Location

2-91 Map