Highways 169/41/78 Interchange
NOW OPEN TO TRAFFIC
Construction Years: 2018-2020
Community: Jackson Township, Louisville Township
Corridor Served:
- US Highway 169
- State Highway 41
- County Highway 78
- County Highway 14
Project Lead: Scott County
Partners: MnDOT, Jackson Township, Louisville Township, SMSC
Contractor: Ames Construction, Inc.
Bid Date: July 31, 2018
Start Date: September 17, 2018
Prepare for new routes through the Highway 169/41/78 intersection. All roads are open to traffic. Use caution and follow directional signs when traveling through the area.
- Watch this video to learn how the new Diverging Diamond Interchange operates. A DDI might feel a bit unusual at first, but with patience and practice, navigating this new way of travel will get easier with each trip.
- En español
- See how to get to Highway 41/Chaska (PDF)
- See how to get to County Highway 78 (PDF)
Highway 169/41/78 Ribbon Cutting Ceremony
Construction Schedule: (dates subject to change)
- Construction crews will be working Monday-Friday, 7 am to 8 pm
- No nighttime work is anticipated at this time
Ch 14 Overpass Photos
-
Construction crews poured concrete for the bridge deck of the new County Highway 14 overpass on April 24, 2019.
-
Another view of the contractor pouring concrete for the new County Highway 14 bridge deck on April 24, 2019. The new overpass is south of the Highways 169/41/78 intersection.
-
Construction crews placed beams that will support the driving surface of the new County Highway 14 overpass over southbound Highway 169 on Jan. 22, 2019
-
Another view of crews placing beams for the new County Highway 14 overpass over southbound Highway 169 on Jan. 22, 2019
-
Construction crews placed beams that will support the driving surface of the new County Highway 14 overpass over northbound Highway 169 in March 2019
-
169 ch 14
Construction Drone Footage:
The following footage shows the progress on the frontage roads on both the North and South sides of 169 as well as the new overpass that is being created.
October 25th, 2019 - May 20th, 2020
June 25th, 2019
October 23, 2018
Watch the Groundbreaking Video Below:
Construction Schedule: (Dates subject to change)
- See the project overview and construction schedule at-a-glance:
- See Winter-Early Spring 2019 construction highlights [PDF]
- Construction crews are constructing a new bridge over Highway 169 just north of County Road 14.
- Crews are constructing a new retaining wall near County Road 78 to support the new frontage road system that will open to traffic in early summer 2019.
- Some utilities continue to be relocated. No planned service disruptions are anticipated during this work. Utility companies will directly contact property owners in advance of any scheduled service disruptions.
Construction Schedule: (Dates subject to change)
- See the project overview and construction schedule at-a-glance:
- See Winter-Early Spring 2019 construction highlights [PDF]
- Construction crews are constructing a new bridge over Highway 169 just north of County Road 14.
- Crews are constructing a new retaining wall near County Road 78 to support the new frontage road system that will open to traffic in early summer 2019.
- Some utilities continue to be relocated. No planned service disruptions are anticipated during this work. Utility companies will directly contact property owners in advance of any scheduled service disruptions.
Drone Progress Photos June 24, 2020
-
Hwy 169 Overpass
-
Northbound Hwy 169
-
Southbound Hwy 169
-
Northbound Hwy 169
-
Hwy 169 Overpass from Hwy 41
-
Southbound Hwy 169
-
Hwy 41 to Hwy 169
-
Overview of Hwy 169 overpass
-
Overview of Hwy 169 overpass
-
T169-06 Drone Progress Photos
-
North view of Hwy 169 Overpass
-
CR 78 to Hwy 169
Drone Progress Photos May 20, 2020
-
Southbound Hwy 169 to Overpass
-
Hwy 169/41/78 Intersection Overview
-
Northbound Hwy 169
-
CR 78 to Hwy 169
-
CR 78 to Hwy 169 Overpass
-
-
-
-
CR 78 overview
-
Description
Scott County and MnDOT designed an interchange at US Highway 169 and Trunk Highway (TH) 41/County Highway (CH) 78. Scott County was successful in obtaining federal funding to expand the scope of the project to include a proposed overpass over US 169 near CH 14 and extension of the frontage road system along the east side of US 169 between CH 78 and CH 14. The expectation is to begin construction in September 2018.
MnDOT has concluded that an Environmental Impact Statement (EIS) is not required and has issued a Negative Declaration Order for the project.
Additional information including notices for upcoming public meetings on the project will be posted on this page as it becomes available.
Purpose & Justification
This project will improve the safety and mobility in this area by removing direct access to US Highway 169. This project is consistent with the long-term vision of converting this segment of US Highway 169 into a freeway.
This project will be funded in part by the Scott County Transportation Sales Tax.
Related Documents
Newsletter #5 - Open House
Newsletter #4 - Layout / EAW
Newsletter #3 - Open House
Newsletter #2 - Open House
-
Christine Dufour
MnDOT Communications Metro DistrictPhone: 651-234-7518